Site Development Project 2019
*Excavation Works @ Road 2 – Sta. 0+000 – 0+010 and Road 1 – Sta. 0+010 – 0+020
*Hauling of Excavated Soil
*Compaction and Sub-Grade Preparation
*Fabrication of Road Formworks
*Installation of Perimeter Fence @ Sta. 0+000 – 0+030 -
SITE DEVELOPMENT PROJECT 2019 (ROAD RE-ROUTING):
*Installation of Perimeter Fence Formworks @ Road 2 Sta. 0+000
*Installation of Perimeter Fence Gate Formworks @ Road 2 Sta. 0+030
*Installation of Color Roof for Perimeter Fence and Gate
*Excavation Works @ Road 2 Sta. 0+000
*Hauling of Excavated Soil
Philippine Science High School – Central Visayas Campus – Argao Cebu
-
SITE DEVELOPMENT 2019
*Backfilling and Compaction (Road 1: Sta. 0+010 – 0+030)
*Sub-Grade Preparation (Road 1: 0+030 – 0+060 ; Road 2: Sta. 0+000 – 0+030) -
SITE DEVELOPMENT 2019
*Backfilling and Compaction (Road 1: Sta. 0+010 – 0+030)
*Sub-Grade Preparation (Road 1: 0+030 – 0+060 ; Road 2: Sta. 0+000 – 0+030) -
SITE DEVELOPMENT 2019
*Backfilling and Compaction (Road 1: Sta. 0+010 – 0+030)
*Sub-Grade Preparation (Road 1: 0+030 – 0+060 ; Road 2: Sta. 0+000 – 0+030) -
SITE DEVELOPMENT 2019
*Backfilling and Compaction (Road 1: Sta. 0+010 – 0+030)
*Sub-Grade Preparation (Road 1: 0+030 – 0+060 ; Road 2: Sta. 0+000 – 0+030) -
SITE DEVELOPMENT 2019
*Backfilling and Compaction (Road 1: Sta. 0+010 – 0+030)
*Sub-Grade Preparation (Road 1: 0+030 – 0+060 ; Road 2: Sta. 0+000 – 0+030) -
SITE DEVELOPMENT 2019
*Backfilling and Compaction (Road 1: Sta. 0+010 – 0+030)
*Sub-Grade Preparation (Road 1: 0+030 – 0+060 ; Road 2: Sta. 0+000 – 0+030) -
SITE DEVELOPMENT 2019
*Laying of Banda-Banda2 (Road 1: STA. 0+030 – 0+060; Road 2: STA. 0+000 – 0+040)
*Installation of Road Formworks @ Road 2: Sta. 0+030 – 0+040 -
SITE DEVELOPMENT 2019
*Laying of Banda-Banda2 (Road 1: STA. 0+030 – 0+060; Road 2: STA. 0+000 – 0+040)
*Installation of Road Formworks @ Road 2: Sta. 0+030 – 0+040 -
SITE DEVELOPMENT 2019
Activities:
*Filling of Aggregate Base Course @ Road 1: Sta. 0+010 – 0+030
*Road Compaction @ Road 1: Sta. 0+010 – 0+030
*Installation of Road Formworks – Right Lane (Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040)
*Concrete Pouring @ Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040 -
SITE DEVELOPMENT 2019
Activities:
*Filling of Aggregate Base Course @ Road 1: Sta. 0+010 – 0+030
*Road Compaction @ Road 1: Sta. 0+010 – 0+030
*Installation of Road Formworks – Right Lane (Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040)
*Concrete Pouring @ Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040 -
SITE DEVELOPMENT 2019
Activities:
*Filling of Aggregate Base Course @ Road 1: Sta. 0+010 – 0+030
*Road Compaction @ Road 1: Sta. 0+010 – 0+030
*Installation of Road Formworks – Right Lane (Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040)
*Concrete Pouring @ Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040 -
SITE DEVELOPMENT 2019
Activities:
*Filling of Aggregate Base Course @ Road 1: Sta. 0+010 – 0+030
*Road Compaction @ Road 1: Sta. 0+010 – 0+030
*Installation of Road Formworks – Right Lane (Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040)
*Concrete Pouring @ Road 1: Sta. 0+050 – 0+060; Road 2: Sta. 0+000 – 0+040 -
SITE DEVELOPMENT 2019
Activities:
Installation of Road Formworks and Scaffoldings (Road 2: Sta. 0+005 – 0+040)
Concrete Pouring @ Road 2: Sta. 0+005 – 0+040 (18cu.m.)
Installation of Road Formworks and Scaffoldings (Road 1: Sta. 0+010 – 0+050) -
SITE DEVELOPMENT 2019
Activities:
Installation of Road Formworks and Scaffoldings (Road 2: Sta. 0+005 – 0+040)
Concrete Pouring @ Road 2: Sta. 0+005 – 0+040 (18cu.m.)
Installation of Road Formworks and Scaffoldings (Road 1: Sta. 0+010 – 0+050) -
“We specialize in Design and Build scheme, providing single-source responsibility for the entire construction process”.
SITE DEVELOPMENT under Design and Build Scheme.
Activities:
*Concrete Pouring @ Road 1: Sta. 0+050 – 0+025 (Right Side only)
*Cutting of Road Conrete Pavement for Blocking
*Excavation and Filling of Aggregate Base Course @ Road 1: Sta. 0+000 – 0+010 (Right Side only)
*Installation of Road Formworks and Scaffolding @ Road 1: Sta. 0+000 – 0+010 (Right Side)
*Concrete Pouring @ Road 1: Sta. 0+000 – 0+025 (Right Side)
*Preparation and Compaction of Soil for Curb and Gutter @ Road 2: Sta. 0+020 – 0+040 (Right Side)
*Installation of Curb and Gutter Formworks and Scaffoldings @ Road 2: Sta. 0+020 – 0+040 (Right Side)
*Filling of Gravel Bedding for Curb and Gutter @ Road 2: Sta. 0+030 – 0+040 (Right Side) -
“We specialize in Design and Build scheme, providing single-source responsibility for the entire construction process”.
SITE DEVELOPMENT under Design and Build Scheme.
Activities:
*Concrete Pouring @ Road 1: Sta. 0+050 – 0+025 (Right Side only)
*Cutting of Road Conrete Pavement for Blocking
*Excavation and Filling of Aggregate Base Course @ Road 1: Sta. 0+000 – 0+010 (Right Side only)
*Installation of Road Formworks and Scaffolding @ Road 1: Sta. 0+000 – 0+010 (Right Side)
*Concrete Pouring @ Road 1: Sta. 0+000 – 0+025 (Right Side)
*Preparation and Compaction of Soil for Curb and Gutter @ Road 2: Sta. 0+020 – 0+040 (Right Side)
*Installation of Curb and Gutter Formworks and Scaffoldings @ Road 2: Sta. 0+020 – 0+040 (Right Side)
*Filling of Gravel Bedding for Curb and Gutter @ Road 2: Sta. 0+030 – 0+040 (Right Side)