16FebJune 15, 2023 DESIGN AND BUILD OF MUNICIPAL SOCIAL WELFARE AND DEVELOPMENT OFFICE BUILDING Activities: -Excavation of Footing Activities: *Concrete Pouring of Columns (Ground Floor to Roof) @ Gridline D1, A3, B3, C3 and D3 *Stripping of Column Steel Forms and Shoarings @ Gridline B3, C3 and D3 *Installation of Column Scaffolds @ Gridline A1, A2 and D2 *Installation of Column Steel Forms and Shoarings @ Gridline A1, A2 and D2 *Concrete Pouring of Columns (Ground Floor to Roof) @ Gridline A1, A2 and D2 *Stripping of Column Steel Forms and Shoarings @ Gridline A2 and D2 *Installation of Column Scaffolds @ Gridline B1 and C1 *Installation of Column Steel Forms and Shoarings @ Gridline B1 and C1 *Chipping of Column in Preparation for Filing of CHB Activities: *Concrete Pouring of Roof Beam @ Grid A & D, Line 1 & 3 *Fabrication of Rafter Truss *Installation of Rafter Truss *Aligning and Full Welding of Roof Trusses *Installation of Sanitary Lines and Fittings from Toilet Rooms to Septic Tank *Stripping of Roof Beam Formworks and Scaffolds *Installation of C-Purlins *Plastering of CHB Interior Walls @ Grid A & D, Line 1 & 3 *Installation of Utility Box and Electrical Roughing-Ins for Lighting Switches *Installation of Wall Angles for Ceiling *Filing of CHB @ Toilet Rooms