DESIGN AND BUILD OF MUNICIPAL SOCIAL WELFARE AND DEVELOPMENT OFFICE BUILDING
Activities: -Excavation of Footing
Activities:
*Concrete Pouring of Columns (Ground Floor to Roof) @ Gridline D1, A3, B3, C3 and D3
*Stripping of Column Steel Forms and Shoarings @ Gridline B3, C3 and D3
*Installation of Column Scaffolds @ Gridline A1, A2 and D2
*Installation of Column Steel Forms and Shoarings @ Gridline A1, A2 and D2
*Concrete Pouring of Columns (Ground Floor to Roof) @ Gridline A1, A2 and D2
*Stripping of Column Steel Forms and Shoarings @ Gridline A2 and D2
*Installation of Column Scaffolds @ Gridline B1 and C1
*Installation of Column Steel Forms and Shoarings @ Gridline B1 and C1
*Chipping of Column in Preparation for Filing of CHB
Activities:
*Concrete Pouring of Roof Beam @ Grid A & D, Line 1 & 3
*Fabrication of Rafter Truss
*Installation of Rafter Truss
*Aligning and Full Welding of Roof Trusses
*Installation of Sanitary Lines and Fittings from Toilet Rooms to Septic Tank
*Stripping of Roof Beam Formworks and Scaffolds
*Installation of C-Purlins
*Plastering of CHB Interior Walls @ Grid A & D, Line 1 & 3
*Installation of Utility Box and Electrical Roughing-Ins for Lighting Switches
*Installation of Wall Angles for Ceiling
*Filing of CHB @ Toilet Rooms