Construction of Multipurpose Building (SB, DSWD, LCR Office)
Activities:
-Hauling of Steel bars
-Fabrication of Lateral Ties, Column and Footing Reinforcement.
-Final clearing/excavation of footing
Activities:
*Reinforcing Steel bars of Columns and Footings
*Installation of scaffoldings
*Installation of Formworks in Columns
*Concrete Pouring of Columns and Footings
Activities:
*Concrete Pouring of 2 columns
*Installation of scaffoldings
*Installation of 2nd Floor Beams Reinforcement
Activities:
*Electrical Works
*Plumbing Works
*Installation of Reinforcing Steel bars in 2nd floor slab
*Installation of Formworks in slab
*Concrete Pouring of 2nd Floor Slab
Construction of Multipurpose Building (SB, DSWD, LCR Office)
Construction of Multipurpose Building (SB, DSWD, LCR Office)