09Jan PROPOSED MOALBOAL BULK WATER SUPPLY (PHASE II) PROPOSED MOALBOAL BULK WATER SUPPLY (PHASE II) ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m ACTIVITES: Tuble: *Excavation – 88ln.m *Breaking of Hard Rock *Concrete cutting of pavement *Sand bedding *Pipelaying of 3″ HDPE Pipe- 78 ln.m *Pipelaying of 4″ HDPE Pipe- 114 ln.m *Backfilling *Laying of Warning Tape Basdiot: *Excavation- 28.47 ln.m *Breaking of Hard rock *Concrete cutting of pavement *Sand Bedding *Pipelaying of 6″ HDPE Pipe- 120 ln.m *Backfilling *Laying of Warning tape Lanao: *Excavation works 3″ HDPE Pipe – 115 ln.m *Excvation works 2″ HDPE Pipe- 189.70 ln.m